4 issues in water utilities
Pure Water Facility project cost increases
Two change orders would add roughly $465,000 combined to the Pure Water Facility project for extra engineering, inspection, and construction services.
Water and Sewer Master Plan map amendment certification
Carroll County is asking the city to certify a map change that moves two parcels from no planned water and sewer service to priority service areas — a big deal for whether those sites can ever be developed with utilities.
Westminster Water Reuse Project bond financing
The city locked in a tax-law step that lets it reimburse early project costs from a low-interest M-WIFA loan — up to $9 million at roughly 1.12% plus $7 million with principal forgiveness that works like a grant. A federal earmark, if it survives the budget, could shrink what the city actually borrows.
Water treatment membrane system purchase
The city bought a $172,857 ultrafiltration membrane system from Filmtec without competitive bidding, citing sole-source justification — part of keeping the water plant running.