Civic Issues
Topics getting the most attention in Westminster public meetings, ranked by how frequently they are discussed.
2 issues in water utilities with medium priority
Pure Water Facility project cost increases
Two change orders would add roughly $465,000 combined to the Pure Water Facility project for extra engineering, inspection, and construction services.
Water and Sewer Master Plan map amendment certification
Carroll County is asking the city to certify a map change that moves two parcels from no planned water and sewer service to priority service areas — a big deal for whether those sites can ever be developed with utilities.