Landfill infrastructure investments
Summary
The county is resurfacing the 40 West Landfill ($974,755) and moving forward with an on-site leachate pretreatment facility projected to save about $1 million a year.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 15, 2026.
Impact analysis
Nearly $1.1 million approved now, with the pretreatment facility's ~$11โ12 million construction expected to pay for itself in about 12 years.
Landfill users and county taxpayers through long-term operating savings.
Water and sewer customers shoulder the rate increases.
Mentions & discussions (2)
Washington County Board of County Commissioners โ Open โ 2026-09-15
The county is resurfacing the 40 West Landfill ($974,755) and moving forward with an on-site leachate pretreatment facility projected to save about $1 million a year.
Washington County Board of County Commissioners โ Open โ 2026-03-31
Water bills go up 5% and sewer 3.5% under rates locked in during the FY25 budget cycle โ about $4.67 and $7.50 more per quarter. The landfill budget grows 2.68% but rates, permits and tipping fees stay flat this year thanks to strong contract revenue.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Washington County, MD
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.