Elections staff have outgrown the Vincent Street building and can't properly store or maintain voting equipment. The county has $8.1 million programmed for a new ~11,000 sq ft facility, with design in FY2028 and construction in FY2029.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
$8.1 million programmed across FY2028–FY2029, roughly $700 per square foot.
Voters countywide get a secure, modern election operation with better polling and early-voting options.
Mentions & discussions (2)
1. Board of County Commissioners - Sep 8, 2026
The county took ownership of the 11-acre former school headquarters at 202 Chesterfield Avenue in Centreville — a surplus property the county can now repurpose or dispose of.
1. Board of County Commissioners (Work) - Mar 31, 2026
Elections staff have outgrown the Vincent Street building and can't properly store or maintain voting equipment. The county has $8.1 million programmed for a new ~11,000 sq ft facility, with design in FY2028 and construction in FY2029.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Queen Anne's County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.