2018 Water and Sewer Plan amendments (June 2026 cycle)
Changing water and sewer category designations decides which properties can get public utility service — and that shapes where new development can and can't happen. These cycle amendments could open some areas to growth while keeping others rural.
WSSC FY 2028 budget and water rate increases
Your water and sewer bills are going up about 5% starting July 1, 2026, as part of WSSC's adopted $1.97 billion budget. Builders will also pay more in hookup fees, which can show up in new-home prices.
Utility Shut-Off Moratorium Request
The council asked the state's Public Service Commission to block utility shutoffs for low-income, senior and medically vulnerable households during extreme weather — and to examine why bills keep spiking, including data centers' role. Speakers described $1,700 electric bills.
WSSC Spending Affordability Limits
Residents are feeling the pinch of high water and sewer bills, leading the council to push for a lower 5% spending cap on WSSC's budget rather than Montgomery County's proposed 7%. Council members also called for better public education explaining how past deferred pipe maintenance impacts current costs.
WSSC FY 2027 water and sewer budget
WSSC's $1.9 billion budget is funded by rates rather than taxes, and both Prince George's and Montgomery County councils must agree before rates take effect. If the two councils don't agree, WSSC's budget is approved as submitted.
Water and sewer category change, 7809 Chrome Road
Seven property applications and countywide redesignations moved through the water and sewer plan, enabling connections and small developments mostly in District 9.
$38.5 Million Stormwater Loan Authorization
The county was scheduled to consider borrowing up to $38.5 million through state water infrastructure loans to pay for stormwater and watershed protection projects. The debt is repaid from the watershed fund, not general tax revenue.
Stormwater Management Fund Budgets
The county was scheduled to consider borrowing up to $38.5 million through state water infrastructure loans to pay for stormwater and watershed protection projects. The debt is repaid from the watershed fund, not general tax revenue.
Public Sewer Capacity in Prince George's County
DC Water reported the January 19 pipe break is repaired and flows restored, but emergency costs are ~$20 million — WSSC's share is 30.9% — with a $128 million six-year rehabilitation plan that could nudge rates up 0.6%.
Stormwater Fund Structural Deficit
The county's stormwater fee hasn't gone up since 1987 while infrastructure has doubled, and maintenance budgets can't keep pace — 50-70 facilities fail each year but only 40-50 can be fixed. Staff warn this could mean another consent decree by 2027.
Sewage odor complaints in Capitol Heights
A Capitol Heights resident says her whole house smells like sewage when running the dishwasher or washing machine, and a senior center off Addison Road had the same problem during lunch. WSSC Water promised to investigate and figure out who's responsible for repairs beyond her property line.
FY 2028-2033 Capital Improvements Program
The six-year capital program, including the capital improvement budget, was part of the hearing. Legislative Attorney Leroy Maddox read potential CIP project listings into the record, and residents commented on infrastructure priorities.