Potomac plant power failure and aging electrical infrastructure
Summary
Last week's power failure at the Potomac Water Filtration Plant disrupted water for most of two counties. WSSC blamed obsolete 1975-era electrical equipment and said an assessment confirms the top three highest-risk projects match the failure points; $11.8 million in electrical upgrades are in the FY 2028 budget.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 8, 2026.
Impact analysis
$11.8 million in electrical upgrades plus $24 million in declared emergency costs absorbed this year.
All water customers in both counties gain reliability from modernized treatment plant power systems.