Street resurfacing and concrete work contract
Summary
With Community Development Block Grant money, the city plans to fully resurface Cherrywood Lane from Greenbelt Road to the roundabout within two years, and has submitted another grant application for the remainder of the road.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 28, 2026.
Impact analysis
Funded through Community Development Block Grant awards.
Drivers and pedestrians along Cherrywood Lane get smoother roads and better sidewalks.
Residents in areas where easement or engineering issues delay sidewalk construction.
Mentions & discussions (3)
General - Oct 28, 2026
With Community Development Block Grant money, the city plans to fully resurface Cherrywood Lane from Greenbelt Road to the roundabout within two years, and has submitted another grant application for the remainder of the road.
City Council - Jun 22, 2026
The council approved up to $1.15 million with VMP for resurfacing streets and concrete repairs. Residents should see paving work around the city.
General - Apr 15, 2026
Building new sidewalks is being slowed by limited funding, easement requirements, and engineering constraints, even with CDBG grant money in play.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenbelt, MD
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.