Duvall Field Phase 2 renovation change orders

Summary

The long-running park renovation needed $355,553 in extra work — tree-preserving paths, guardrails, security cameras, and sod. Councilmembers pressed staff on why the costs arose and what will prevent future change orders.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jan 27, 2026.

Impact analysis

💰Financial impact

Adds $355,553 to the project cost, drawn from the project contingency.

✅Who benefits

Park users and District 2 residents who will see the renovation completed, targeted for early summer.

⚠️Who could be affected

Taxpayers bear the added cost, which staff attributed partly to engineering errors and an accelerated design timeline.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for College Park

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.