Liberty Water Storage Tank Booster Pump Station Project
Summary
A $2.4 million project — 37% under estimate — will give the Freedom District's high-elevation water zone a redundant supply via a new booster station and 2,400 feet of new water main along Johnsville Road.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 9, 2026.
Impact analysis
Came in roughly $1.37 million below the $3.83 million engineer's estimate — a savings for water customers.
Water customers in the high-elevation zone of the Freedom District in Commissioner District 5.
Mentions & discussions (2)
Board of County Commissioners Open Session - Jul 9, 2026
A $2.4 million project — 37% under estimate — will give the Freedom District's high-elevation water zone a redundant supply via a new booster station and 2,400 feet of new water main along Johnsville Road.
Board of County Commissioners Open Session - May 28, 2026
A $99,789 inspection contract keeps the Freedom District water project on track; the construction contract itself will be much cheaper than budgeted, which could ease pressure on water rates.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Carroll County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.