The county wants to remove a decades-old 100-foot no-cut buffer along Cox Road at the Huntingtown park so it can pave and expand the parking lot, fix stormwater and add ADA access. The 35-foot setback stays, but final action waits 10 days after the hearing.

At a glance

Total mentions
5
Last 30 days
0

Last discussed Jul 28, 2026.

Impact analysis

💰Financial impact

About $3 million in construction from the Marley Run CIP, which has roughly $1.2 million on hand plus $2.5 million more requested in FY 27.

✅Who benefits

Families and leagues that use the park's three ball fields daily, plus players needing accessible pathways and parking.

⚠️Who could be affected

None identified, though neighbors along Cox Road care about how the reduced berm will look.

Mentions & discussions (5)

MeetingJul 28, 2026approved

Regular Meeting of the Board of County Commissioners - Jul 28, 2026

Confusion after last week's meeting prompted the board to formally clarify that nothing changed — Resolution 3-92 and the Marley Run park buffer stand as-is.

MeetingJul 21, 2026approved

Regular Meeting of the Board of County Commissioners - Jul 21, 2026

The Board adopted the resolution addressing Condition 9 of Resolution 3-92, with discussion indicating the outcome preserves the status quo — the existing 35-foot Cox Road setback — rather than removing the buffer as earlier proposed.

MeetingApr 28, 2026

Regular Meeting of the Board of County Commissioners - Apr 28, 2026

The county wants to reduce a 100-foot no-cut buffer from a 1989 transfer zone resolution to 35 feet to fix stormwater and repave the parking lot, but neighbors pushed back. The board put the project on hold for 60 days and will meet with the HOA.

MeetingApr 14, 2026tabled

Regular Meeting of the Board of County Commissioners - Apr 14, 2026

The county wants to remove a decades-old 100-foot no-cut buffer along Cox Road at the Huntingtown park so it can pave and expand the parking lot, fix stormwater and add ADA access. The 35-foot setback stays, but final action waits 10 days after the hearing.

MeetingFeb 18, 2026

Planning Commission Regular Meeting Agenda - Feb 18, 2026

Parks & Recreation wants the 100-foot buffer cut to 35 feet so it can pave the parking lot, fix stormwater that's threatening the lower ball field, and improve ADA access. The commission backed the change, which now goes to the County Commissioners with a single public hearing.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Calvert County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.