Critical PriorityZoningopen

Data Center Zoning Conditions (Text Amendment #26-23)

Summary

The Board directed staff to pursue extending the data center moratorium, removing data centers as a permitted use, and rezoning heavy industrial properties. The incoming board sworn in December 15 will make the final calls, but the process clock is now running. Residents strongly support action.

At a glance

Total mentions
18
Last 30 days
0

Last discussed Sep 22, 2026.

Impact analysis

💰Financial impact

Staff identified no direct fiscal impact so far, but data centers elsewhere on the grid could drive up residents' electric bills.

✅Who benefits

Residents near the Camp Kanoy Road area and across the county who oppose hyperscale data center development.

⚠️Who could be affected

Data center developers and landowners seeking industrial development of rezoned parcels.

Mentions & discussions (18)

MeetingSep 22, 2026

Regular Meeting of the Board of County Commissioners - Sep 22, 2026

The Board directed staff to pursue extending the data center moratorium, removing data centers as a permitted use, and rezoning heavy industrial properties. The incoming board sworn in December 15 will make the final calls, but the process clock is now running. Residents strongly support action.

MeetingAug 18, 2026

Regular Meeting of the Board of County Commissioners - Aug 18, 2026

The county considered pausing all data center site plan approvals for six months while it studies impacts like noise, water use, and power demands and writes new zoning rules. A large-scale data center application is already in, and more are expected.

MeetingJul 28, 2026

Regular Meeting of the Board of County Commissioners - Jul 28, 2026

Speakers pressed the board to act on the data center moratorium, with the vote scheduled for August 18. The county also confirmed AWS has no plans to resubmit its concept plan, though it hasn't officially withdrawn.

MeetingJun 17, 2026

Planning Commission Public Hearing - Jun 17, 2026

The data center text amendment (#26-23) is still being drafted and wasn't heard, but it came up repeatedly — the commission stripped data-center language out of the buffer amendment to avoid prejudging it, and a resident warned about power costs, grid reliability, and pollution.

MeetingJun 2, 2026

Regular Meeting of the Board of County Commissioners - Jun 2, 2026

The board is shaping the county's rules for data centers, taking up the Planning Commission's comments on Text Amendment #26-23 and the Environmental Commission's warnings about environmental impacts. What standards get adopted will decide where and under what conditions data centers can operate here.

MeetingMay 20, 2026

Planning Commission Regular Meeting Agenda - May 20, 2026

Residents are pushing hard on the pending data center zoning amendments — some say setbacks, walls, and buffers won't stop low-frequency noise and fines are too small to deter billion-dollar companies; others say the fears are overblown and the county needs the revenue. The commission is expected to forward recommendations to the BOCC.

MeetingApr 28, 2026

Regular Meeting of the Board of County Commissioners - Apr 28, 2026

SMECO was scheduled to brief the Board on how large data center customers could affect the electric grid and ratepayers. State law puts upgrade costs on the developers, not necessarily local households.

MeetingApr 21, 2026

Planning Commission Regular Meeting Agenda - Apr 21, 2026

The county is drafting extra conditions for data centers after the AWS/Camp Conoy controversy. Commissioners want grandfathering to apply only when construction starts, 1,200-foot setbacks, tough noise limits (45 dBA night, 40 dBC low-frequency), berms, decommissioning bonds, and limited generator testing hours.

MeetingApr 15, 2026

Joint Special Meeting of the Calvert County Planning Commission and Calvert County Environmental Commission - Apr 15, 2026

Since the moratorium failed, the fallback is text amendments — including removing data centers from I-1 light industrial. But officials warned that if data centers aren't carefully defined, they could sneak in as 'warehouses' almost anywhere, including town centers.

MeetingApr 14, 2026denied

Regular Meeting of the Board of County Commissioners - Apr 14, 2026

Residents from Lusby and Camp Conoy demanded answers on the Constellation/Amazon data center plans, saying the rezoning bypassed normal neighbor notification and that 400-foot setbacks are too close. Commissioner Hart's motion to explore a one-year moratorium failed, and Commissioner Hance withdrew a proposal to require developer agreements before permits.

MeetingApr 7, 2026

Regular Meeting of the Board of County Commissioners - Apr 7, 2026

AWS has floated a data center on the Constellation Energy property in Lusby, and residents packed public comment asking the county to slow down. A 24-month pause failed 3-2, but the board did vote to ban data centers from I-1 zoning and to study how future data center tax revenue could be split between taxpayers, schools, reserves and community needs.

MeetingMar 26, 2026

Special Meeting of the Board of County Commissioners - Mar 26, 2026

Amazon is evaluating a data center campus next to the Calvert Cliffs nuclear plant — up to eight buildings on already-zoned heavy industrial land, so no rezoning fight. The pitch: no new water demand, no new public utilities, hundreds of high-paying jobs, and tens of millions in new tax revenue. It's still preliminary — no site plans filed, no agreements signed.

MeetingMar 18, 2026

Planning Commission Regular Meeting Agenda - Mar 18, 2026

The county is drafting extra conditions for any future data center — no groundwater cooling, water-use plans, applicant-paid infrastructure, cleaner generators. No project has been submitted yet, but an MDE application reveals a 500 MW, seven-building project proposed near Calvert Cliffs, and residents are worried about noise, water, and the Bay.

MeetingMar 10, 2026

Regular Meeting of the Board of County Commissioners - Mar 10, 2026

The county is drafting conditions — water-use plans, generator emissions standards, third-party review — that would apply to any data center. Commissioners are split and stress that nothing moves without public support; a community open house is set for March 26 at Calvert Middle School.

MeetingMar 3, 2026

Regular Meeting of the Board of County Commissioners - Mar 3, 2026

A resident's written comment laid out a documented timeline of county negotiations with a data center developer, including a signed non-disclosure agreement and state findings of adverse effects on historic sites. He urged the board to restore the data center conditions work session to the agenda and adopt strong water, noise, and oversight protections.

MeetingFeb 24, 2026

Regular Meeting of the Board of County Commissioners - Feb 24, 2026

The board again deferred Proposed Text Amendment #26-23, which would set conditions for data centers. Residents criticized the county's precedent of granting repeated temporary use-and-occupancy permits to non-compliant businesses and questioned how the rules would actually be enforced.

MeetingFeb 10, 2026

Regular Meeting of the Board of County Commissioners - Feb 10, 2026

Staff drafted first-round conditions for data centers — closed-loop water cooling, no well drilling for cooling, rooftop stormwater reuse, full infrastructure cost responsibility, and EPA Tier 4 generators. Commissioners want more options and a dedicated follow-up work session in two weeks, and acknowledged state or federal preemption could limit county authority.

MeetingJan 13, 2026

Regular Meeting of the Board of County Commissioners - Jan 13, 2026

A resident flagged a data center campus project in southern Calvert, citing an MDE permit number, concerns about the historical tobacco barns and Parent's Park, and urging the county to require on-site power generation.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Calvert County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.